City of Live Oak Trail Project 

3,000 Linear Foot x 6 foot wide concrete sidewalk. Project required site work, grading, and haul-off of existing soil and tree debris to make room for concrete trucks and to prepare sidewalk layout. Project management designed the job for three concrete pours at 1,000 LF each pour. Project was delivered ahead of schedule. Zero infractions. Zero violations. Zero environmental penalties. 

Proposed Elevation at 18" Below Existing Grade. 2x6 Timber Layout. 
Proposed Elevation at 18" Below Grade. 2x6 Timber Layout. 
2x6 Timber Forms Installed at 6" Gap to Grade.  12" 3/4 Base Laid and Compacted Wet to 95%.
#5 Reinforcement Bar Installed at 12" On Center at 1,000 Linear Feet. 
#5 Reinforcement Bar Installed at 12" On Center at 1,000 Linear Feet. 
1,000 Linear feet Inspected for  2% Slope at Each Radius. Ready for Concrete Pour. 

1,000 Linear Feet x 6 ' Wide x 6" Thick Class C Concrete at Day 1 After Pour.  
1,000 Linear Feet x 6 ' Wide x 6" Thick Class C Concrete at Day 1 After Pour. 
1,000 Linear Feet x 6 ' Wide x 6" Thick Class C Concrete at Day 1 After Pour. 
1,000 Linear Feet at Day 7 After Concrete Pour. 
3,000 Linear Feet at 80 Day Total Cure. Soil Tracking Raked, and Sidewalk Edges Filled in with Native Soil. 
3,000 Linear Feet Sidewalk Swept. Ready for Public Use. 